docs(timeline): update schedule adherence Day 99 (2026-04-09) cycle-3
CI / benchmark-publish (pull_request) Waiting to run
CI / lint (pull_request) Successful in 37s
CI / build (pull_request) Successful in 38s
CI / quality (pull_request) Successful in 50s
CI / push-validation (pull_request) Successful in 19s
CI / helm (pull_request) Successful in 37s
CI / typecheck (pull_request) Successful in 1m15s
CI / security (pull_request) Successful in 1m17s
CI / benchmark-regression (pull_request) Waiting to run
CI / e2e_tests (pull_request) Successful in 3m54s
CI / integration_tests (pull_request) Successful in 4m23s
CI / unit_tests (pull_request) Successful in 7m52s
CI / docker (pull_request) Successful in 15s
CI / coverage (pull_request) Successful in 13m34s
CI / status-check (pull_request) Successful in 1s

- Append Day 99 schedule adherence entry with full milestone, track,
  developer, task inventory, and story point allocation tables
- Update gantt chart: today marker 2026-04-09, footer, update log
- Update Current Status Summary: 172 open PRs, ~3259 open bugs
- Milestone completions: M3 50% (245/492), M4 54% (108/200),
  M5 60% (130/218), M6 19% (193/1009), M7 42% (150/361),
  M8 46% (422/928), M9 29% (129/446)
- Bug count tripled: ~878 to ~3259 (UAT pool high-velocity filing)
- Scope expanded across all milestones due to agent-driven issue creation
This commit is contained in:
2026-04-09 10:40:30 +00:00
parent a3762a4cc2
commit 77b9325be9
+107 -14
View File
@@ -10,25 +10,24 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
@startgantt
title CleverAgents Core — Epic-Level Project Schedule
footer Generated 2026-04-08 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~878 open bugs | 1 open PR | Session 4 active
footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3259 open bugs | 172 open PRs | Session 4 active
Project starts 2026-02-03
saturday are closed
sunday are closed
printscale weekly zoom 2
today is 2026-04-08
today is 2026-04-09
today is colored in #FF6666
' ================================================================
' GANTT CHART UPDATE LOG (Day 98 — 2026-04-08)
' Changes: Day 98 refresh. New build session #4799 launched 2026-04-08.
' Open PRs: 108→1 (massive merge wave). Open bugs: ~878 (stable).
' M3 73% (235/320), M4 67% (108/161), M5 71% (130/183), M6 29% (188/638, scope expanded!),
' M7 48% (150/312), M8 47% (403/855).
' Progress since Day 96: M3 +8%, M4 +7%, M5 +3%, M7 +5%, M8 +1%.
' M6 scope expanded massively: 327→638 total issues (+311 new issues added).
' Session 4 active. Session tracker issue: #4799.
' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09)
' Changes: Day 99 refresh. Session 4 active (issue #4799), 32 parallel workers.
' Open PRs: 1→172 (+171 new PRs opened by agents). Open bugs: ~878→~3259 (+2381 new UAT bugs!).
' M3 50% (245/492), M4 54% (108/200), M5 60% (130/218), M6 19% (193/1009, scope expanded!),
' M7 42% (150/361), M8 46% (422/928), M9 29% (129/446).
' Massive scope expansion across all milestones due to agent-driven issue creation.
' Bug count tripled: ~878→~3259 (UAT pool filing bugs at very high velocity).
' ================================================================
<style>
@@ -1965,13 +1964,13 @@ This section provides a high-level overview of the CleverAgents implementation r
### Current Status Summary
As of Day 98 (2026-04-08), the project has **1 open PR** (down from 108massive merge wave!) and **~1458 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~878 open bugs** (stable). M8 (v3.7.0) is now **47% complete** (403/855 issues closed). M3 (v3.2.0) at **73%** (235/320), M4 (v3.3.0) at **67%** (108/161), M5 (v3.4.0) at **71%** (130/183), M6 (v3.5.0) at **29%** (188/638 — scope massively expanded from 327 to 638 issues), M7 (v3.6.0) at **48%** (150/312).
As of Day 99 (2026-04-09), the project has **172 open PRs** (up from 1 — agents opened 171 new PRs) and **~2281 open issues** across active milestones. **Session 4 is active (launched 2026-04-08, issue #4799) with 32 parallel workers and full supervisor fleet**. Bug count is **~3,259 open bugs** (up from ~878 — UAT pool filing spec compliance issues at very high velocity). M8 (v3.7.0) is now **46% complete** (422/928 issues closed). M3 (v3.2.0) at **50%** (245/492), M4 (v3.3.0) at **54%** (108/200), M5 (v3.4.0) at **60%** (130/218), M6 (v3.5.0) at **19%** (193/1009 — scope massively expanded from 638 to 1009 issues), M7 (v3.6.0) at **42%** (150/361), M9 (v3.8.0) at **29%** (129/446).
**M1, M2 fully complete. M3 (v3.2.0)**: 73% complete (235/320), 85 open issues. **M4 (v3.3.0)**: 67% complete (108/161), 53 open issues. **M5 (v3.4.0)**: 71% complete (130/183), 53 open issues. **M6 (v3.5.0)**: 29% complete (188/638), 450 open issues — scope expanded massively (+311 new issues). **M7 (v3.6.0)**: 48% complete (150/312), 162 open issues. **M8 (v3.7.0)**: 47% complete (403/855), 452 open issues. All milestones M3-M7 are **overdue**; M8 is in active v3.7.0 development.
**M1, M2 fully complete. M3 (v3.2.0)**: 50% complete (245/492), 247 open issues. **M4 (v3.3.0)**: 54% complete (108/200), 92 open issues. **M5 (v3.4.0)**: 60% complete (130/218), 88 open issues. **M6 (v3.5.0)**: 19% complete (193/1009), 816 open issues — scope expanded massively (+371 new issues since Day 98). **M7 (v3.6.0)**: 42% complete (150/361), 211 open issues. **M8 (v3.7.0)**: 46% complete (422/928), 506 open issues. **M9 (v3.8.0)**: 29% complete (129/446), 317 open issues. All milestones M3-M7 are **overdue**; M8/M9 are in active development.
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~878 Open Bugs — Session 4 Active (Day 98: New Session #4799, M6 Scope Expanded +311 Issues)"
!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — ~3,259 Open Bugs — Session 4 Active (Day 99: Bug Count Tripled, M6 Scope Expanded +371 Issues, 172 Open PRs)"
All milestones M3 through M7 have passed their target dates. **Session 4 launched 2026-04-08 with 32 parallel workers**. Open PRs at **1** (down from 108massive merge wave). Open bugs at **~878** (stable). Session tracker issue: #4799. **Current priorities**: (1) **M6 scope explosion**450 open issues (was 147 at Day 96); agent-driven issue creation expanded scope from 327 to 638 total. (2) **Triage ~878 open bugs** — systematic review required. (3) **Continue M8 push**47% complete, 452 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 73% (85 open), M4 at 67% (53 open), M5 at 71% (53 open).
All milestones M3 through M7 have passed their target dates. **Session 4 active (launched 2026-04-08, issue #4799) with 32 parallel workers**. Open PRs at **172** (up from 1 — agents opened 171 new PRs). Open bugs at **~3,259** (tripled from ~878 — UAT pool filing bugs at very high velocity). Session tracker issue: #4799. **Current priorities**: (1) **Bug triage crisis**~3,259 open bugs (was ~878 at Day 98); UAT pool is discovering spec compliance issues at very high velocity. (2) **M6 scope explosion** — 816 open issues (was 450 at Day 98); scope expanded from 638 to 1009 total. (3) **Continue M8/M9 push**M8 at 46% (506 open), M9 at 29% (317 open). (4) **Clear M3/M4/M5 backlogs** — M3 at 50% (247 open), M4 at 54% (92 open), M5 at 60% (88 open).
### Parallel Workstreams
@@ -5223,3 +5222,97 @@ Story points per developer per milestone.
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |
### 2026-04-09 (Day 99)
**Summary**
Status: Behind 20+d
Deadline risk: CRITICAL
**Notes**
- Day 99 update (2026-04-09). Session 4 remains active (issue #4799) with 32 parallel workers and full supervisor fleet.
- Open PRs grew from 1 to 172 (+171 new PRs opened by agents across docs, spec, fix, and feat categories).
- Open bugs tripled: ~878 → ~3,259 (+2,381 new UAT bugs). UAT pool supervisor is filing spec compliance issues at very high velocity.
- Milestone scope expanded significantly across all milestones due to agent-driven issue creation: M3 (320→492, +172), M4 (161→200, +39), M5 (183→218, +35), M6 (638→1009, +371), M7 (312→361, +49), M8 (855→928, +73), M9 (N/A→446 total).
- Milestone completions (Day 99 cycle-3): M3 50% (245/492), M4 54% (108/200), M5 60% (130/218), M6 19% (193/1009), M7 42% (150/361), M8 46% (422/928), M9 29% (129/446).
- Apparent completion percentages dropped across M3-M8 due to scope expansion outpacing closures: M3 73%→50%, M4 67%→54%, M5 71%→60%, M6 29%→19%, M7 48%→42%, M8 47%→46%.
- Critical UAT bugs filed include: #5467 (GRAPH actor subgraph nodes stub-only — Critical), #5479 (GitWorktreeSandbox merge conflict not surfaced — Critical), #5489 (E2E test missing plan diff step — Critical), #5506 (ToolRunner falls through to host on CONTAINER_REF — Critical), and 2,380+ additional UAT spec compliance bugs.
- All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development.
- 172 open PRs include multiple timeline update attempts (PRs #5448, #5214, #5185, #5085, #5578) and feature/fix PRs (#5271 ACMS ProjectIndexer, #5276 context settings defaults, #5286 orchestrator scaling to 32 workers).
#### Milestone forecast
| Milestone | Target -> ETA | Delta | Risk |
|-----------|---------------|-------|------|
| M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE |
| M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE |
| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-20 | +83d | CRITICAL — 247 open issues; 50% complete (scope expanded 320→492) |
| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-18 | +77d | CRITICAL — 92 open issues; 54% complete (scope expanded 161→200) |
| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-15 | +70d | HIGH — 88 open issues; 60% complete (scope expanded 183→218) |
| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-08-15 | +157d | CRITICAL — 816 open issues; 19% complete (scope expanded 638→1009) |
| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-20 | +84d | HIGH — 211 open issues; 42% complete (scope expanded 312→361) |
| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-25 | N/A | HIGH — 506 open issues; 46% complete (scope expanded 855→928) |
| M9 (v3.8.0) | (no deadline) -> ETA 2026-08-15 | N/A | MEDIUM — 317 open issues; 29% complete |
#### Track forecast
| Track | Status | ETA | Risk | Blocking |
|-------|--------|-----|------|----------|
| Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None |
| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-15 | HIGH | 88 open issues in v3.4.0; UAT bugs #5479 (sandbox merge conflict), #5482 (resource remove no link check) |
| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-18 | CRITICAL | 92 open issues in v3.3.0; UAT bugs #5467 (GRAPH subgraph stub), #5475 (actor version field), #5471 (missing LLM fields) |
| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-20 | CRITICAL | 247 open issues in v3.2.0; scope expanded +172 new issues; #5489 (E2E missing plan diff) |
| Track Q (Quality automation) | Ongoing | N/A | CRITICAL | ~3,259 open bugs (tripled from ~878); UAT pool filing at very high velocity |
| Track T (Testing) | Active | Ongoing | HIGH | 172 open PRs need review; #5506 (ToolRunner CONTAINER_REF fallthrough) critical |
#### Developer forecast
| Name | Days Ahead/Behind | Availability | Risk | Focus |
|------|-------------------|--------------|------|-------|
| Jeff | -24d behind | active | HIGH | Session 4 supervisor; M3/M4/M5 backlog clearance; architecture oversight; 172 open PRs |
| Luis | -24d behind | active | HIGH | M6 (v3.5.0) features; security hardening; PR review pool; UAT bug triage |
| Hamza | -24d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; UAT bug fixes (#5479, #5482) |
| Aditya | -24d behind | active | HIGH | M5 features; TDD counterparts; domain model work; ACMS ProjectIndexer (#5271) |
| Brent | -24d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; ~3,259 open bugs triage |
| Rui | -24d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing |
| Mike/Brian | N/A | standby | LOW | Infrastructure support |
#### Task inventory
Milestone per developer as of Day 99 cycle-3 (2026-04-09).
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 |
| M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 247 open | 245/492 |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 92 open | 108/200 |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 88 open | 130/218 |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | 816 open | 193/1009 |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 211 open | 150/361 |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 506 open | 422/928 |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 317 open | 129/446 |
| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~2281 open** | **1473/3750 closed** |
Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 99 cycle-3 (2026-04-09). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at very high velocity across all milestones. Scope expanded significantly: M3 (+172), M4 (+39), M5 (+35), M6 (+371), M7 (+49), M8 (+73), M9 (new: 446 total). Open bugs tripled from ~878 to ~3,259 due to UAT pool filing spec compliance issues at high velocity. Open PRs grew from 1 to 172 (+171 new PRs).
#### Story point allocation
Story points per developer per milestone.
| Milestone | Jeff | Aditya | Luis | Hamza | Brent | Rui | Unassigned | Total |
|-----------|------|--------|------|-------|-------|-----|------------|-------|
| M1 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~172 SP |
| M2 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~208 SP |
| M3 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~104 SP |
| M4 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~126 SP |
| M5 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~129 SP |
| M6 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M7 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~100 SP |
| M8 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M9 | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| M6+ | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~TBD SP |
| **Total** | N/A | N/A | N/A | N/A | N/A | N/A | N/A | ~1649 SP |