From 49bfcca55b990c485e495709900a67b9a16090cc Mon Sep 17 00:00:00 2001 From: CleverThis Date: Thu, 9 Apr 2026 12:41:48 +0000 Subject: [PATCH] docs(timeline): update schedule adherence Day 99 (2026-04-09) cycle-4 - Append Day 99 schedule adherence entry with full milestone, track, developer, task inventory, and story point allocation tables - Update gantt chart: today marker 2026-04-09, footer, update log - Update Current Status Summary: 172 open PRs, ~3343 open bugs - Milestone completions: M2 98% (108/110), M3 49% (247/501), M4 53% (108/203), M5 59% (130/220), M6 19% (193/1012), M7 40% (150/371), M8 46% (422/928), M9 29% (130/452) - Bug count tripled: ~878 to ~3343 (UAT pool high-velocity filing) - Scope expanded across all milestones; M9 closed 1 issue --- docs/timeline.md | 121 +++++++++++++++++++++++++++++++++++++++++------ 1 file changed, 107 insertions(+), 14 deletions(-) diff --git a/docs/timeline.md b/docs/timeline.md index e9a3b5316..166537812 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,25 +10,24 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-08 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~878 open bugs | 1 open PR | Session 4 active +footer Generated 2026-04-09 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3343 open bugs | 172 open PRs | Session 4 active Project starts 2026-02-03 saturday are closed sunday are closed printscale weekly zoom 2 -today is 2026-04-08 +today is 2026-04-09 today is colored in #FF6666 ' ================================================================ -' GANTT CHART UPDATE LOG (Day 98 — 2026-04-08) -' Changes: Day 98 refresh. New build session #4799 launched 2026-04-08. -' Open PRs: 108→1 (massive merge wave). Open bugs: ~878 (stable). -' M3 73% (235/320), M4 67% (108/161), M5 71% (130/183), M6 29% (188/638, scope expanded!), -' M7 48% (150/312), M8 47% (403/855). -' Progress since Day 96: M3 +8%, M4 +7%, M5 +3%, M7 +5%, M8 +1%. -' M6 scope expanded massively: 327→638 total issues (+311 new issues added). -' Session 4 active. Session tracker issue: #4799. +' GANTT CHART UPDATE LOG (Day 99 — 2026-04-09) +' Changes: Day 99 refresh. Session 4 active (issue #4799), 32 parallel workers. +' Open PRs: 1→172 (+171 new PRs opened by agents). Open bugs: ~878→~3343 (+2465 new UAT bugs!). +' M3 49% (247/501), M4 53% (108/203), M5 59% (130/220), M6 19% (193/1012, scope expanded!), +' M7 40% (150/371), M8 46% (422/928), M9 29% (130/452). +' Massive scope expansion across all milestones due to agent-driven issue creation. +' Bug count tripled: ~878→~3343 (UAT pool filing bugs at very high velocity). ' ================================================================