[AUTO-TIME-1] Update timeline: schedule adherence 2026-04-17
CI / lint (pull_request) Successful in 41s
CI / quality (pull_request) Successful in 52s
CI / security (pull_request) Successful in 1m7s
CI / typecheck (pull_request) Successful in 1m23s
CI / build (pull_request) Successful in 47s
CI / push-validation (pull_request) Successful in 23s
CI / helm (pull_request) Successful in 32s
CI / unit_tests (pull_request) Successful in 6m0s
CI / docker (pull_request) Successful in 1m39s
CI / integration_tests (pull_request) Successful in 9m44s
CI / coverage (pull_request) Successful in 11m36s
CI / status-check (pull_request) Successful in 3s
CI / lint (pull_request) Successful in 41s
CI / quality (pull_request) Successful in 52s
CI / security (pull_request) Successful in 1m7s
CI / typecheck (pull_request) Successful in 1m23s
CI / build (pull_request) Successful in 47s
CI / push-validation (pull_request) Successful in 23s
CI / helm (pull_request) Successful in 32s
CI / unit_tests (pull_request) Successful in 6m0s
CI / docker (pull_request) Successful in 1m39s
CI / integration_tests (pull_request) Successful in 9m44s
CI / coverage (pull_request) Successful in 11m36s
CI / status-check (pull_request) Successful in 3s
This commit is contained in:
+18
-8
@@ -10,14 +10,14 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto
|
||||
@startgantt
|
||||
|
||||
title CleverAgents Core — Epic-Level Project Schedule
|
||||
footer Generated 2026-04-15 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 257 open PRs | Session 5 active
|
||||
footer Generated 2026-04-17 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | ~3 open bugs | 328 open PRs | Session 4 active
|
||||
|
||||
Project starts 2026-02-03
|
||||
saturday are closed
|
||||
sunday are closed
|
||||
printscale weekly zoom 2
|
||||
|
||||
today is 2026-04-15
|
||||
today is 2026-04-17
|
||||
today is colored in #FF6666
|
||||
|
||||
' ================================================================
|
||||
@@ -49,6 +49,16 @@ today is colored in #FF6666
|
||||
' v3.8.0: 29% (145/509), v3.9.0: 41% (24/59).
|
||||
' Active milestone: v3.2.0 (933 open), v3.5.0 (1,107 open).
|
||||
' ================================================================
|
||||
' ================================================================
|
||||
' GANTT CHART UPDATE LOG (Day 107 - 2026-04-17)
|
||||
' Changes: Day 107 refresh (cycle 1). Session 4 active (issue #4799, 32 workers).
|
||||
' v3.0.0 CLOSED (100%, 0 open/164 closed), v3.1.0 CLOSED (100%, 0 open/108 closed).
|
||||
' M3 (v3.2.0) 25.0% (323/1291, 968 open), M4 (v3.3.0) 34.9% (118/338, 220 open),
|
||||
' M5 (v3.4.0) 35.6% (158/444, 286 open), M6 (v3.5.0) 17.9% (247/1377, 1130 open),
|
||||
' M7 (v3.6.0) 32.8% (162/494, 332 open), M8 (v3.7.0) 41.9% (438/1046, 608 open),
|
||||
' M9 (v3.8.0) 28.2% (144/511, 367 open), v3.9.0 37.5% (24/64, 40 open).
|
||||
' Open PRs: 257->328 (+71). AUTO-BUG-SUP frozen alert (issue #10222).
|
||||
' ================================================================
|
||||
|
||||
<style>
|
||||
ganttDiagram {
|
||||
@@ -249,7 +259,7 @@ ganttDiagram {
|
||||
|
||||
[Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days
|
||||
[M3] starts at [M2]'s end
|
||||
[M3] is 28% completed
|
||||
[M3] is 25% completed
|
||||
[M3] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.3.0 MILESTONE ─────────────────────────────────────────
|
||||
@@ -270,13 +280,13 @@ ganttDiagram {
|
||||
|
||||
[Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days
|
||||
[M4] starts at [M3]'s end
|
||||
[M4] is 46% completed
|
||||
[M4] is 35% completed
|
||||
[M4] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
[Security + Safety Hardening (#362)] as [SEC] on {Luis} requires 3 days
|
||||
[SEC] starts 2026-03-02
|
||||
[SEC] is 80% completed
|
||||
[SEC] is 28% completed
|
||||
[SEC] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Provider Fixes + Runtime (#363)] as [PROV] on {Luis} requires 2 days
|
||||
@@ -301,12 +311,12 @@ ganttDiagram {
|
||||
|
||||
[ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days
|
||||
[M5] starts at [M4]'s end
|
||||
[M5] is 40% completed
|
||||
[M5] is 36% completed
|
||||
[M5] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
[Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days
|
||||
[M6] starts at [M5]'s end
|
||||
[M6] is 17% completed
|
||||
[M6] is 18% completed
|
||||
[M6] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
|
||||
@@ -317,7 +327,7 @@ ganttDiagram {
|
||||
|
||||
[Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days
|
||||
[LARGE] starts 2026-03-17
|
||||
[LARGE] is 35% completed
|
||||
[LARGE] is 42% completed
|
||||
[LARGE] is colored in LightSkyBlue/SteelBlue
|
||||
|
||||
' ── v3.5.0 MILESTONE ─────────────────────────────────────────
|
||||
|
||||