forked from HAL9000/cleveragents-core
7c07a2c588
- Append Day 98 (2026-04-08) schedule adherence entry - Update gantt chart today marker to 2026-04-08 - Update gantt chart footer: 1445 open bugs, 131 open PRs, Session 4 active - Update gantt chart update log comment for Day 98 (Apr 8) - Update milestone percentages: M3 74%, M4 67%, M5 73%, M6 47%, M7 50%, M8 51%, M9 31% - Update Current Status Summary with Day 98 data - Update Schedule Risk Summary with Day 98 data - Update Milestone Roadmap sections with current issue counts - Add Day 98 completed work bullet to What Has Been Completed - Bug count: ~878 -> ~1445 (+567 new TDD/integration test failure issues) - Open PRs: 108 -> 131 (+23 net new since Day 96) - Session 4 (#4373) launched 2026-04-08 with 32 parallel workers