- Update gantt chart today marker to 2026-04-08 (both charts) - Update gantt chart footer: 1 open PR, ~878 open bugs, Session 4 active - Update GANTT CHART UPDATE LOG to Day 98 with session #4799 details - Update Current Status Summary: Day 98, Session 4, 1 PR, M6 scope explosion - Add Day 98 completed work bullet to What Has Been Completed - Append Day 98 schedule adherence entry with all required tables Key changes: - M6 scope expanded 327→638 (+311 issues), completion 55%→29% - Open PRs dropped 108→1 (massive merge wave) - M3 73% (235/320), M4 67% (108/161), M5 71% (130/183) - M7 48% (150/312), M8 47% (403/855) - Session 4 launched (issue #4799) with 32 parallel workers - UAT bug #4798: agents resource show missing 5 spec-required panels - Spec restructure proposal: issue #4807 (needs feedback)