diff --git a/docs/timeline.md b/docs/timeline.md index c12f05d9d2..6ce580d345 100644 --- a/docs/timeline.md +++ b/docs/timeline.md @@ -10,7 +10,7 @@ The following chart shows all 29 epics across 9 legendary workstreams, 7 milesto @startgantt title CleverAgents Core — Epic-Level Project Schedule -footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 878 open bugs | 183 open PRs | Session 3 active +footer Generated 2026-04-05 | 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers | ~1650 SP | 859 open bugs | 134 open PRs | Session 3 active Project starts 2026-02-03 saturday are closed @@ -22,11 +22,10 @@ today is colored in #FF6666 ' ================================================================ ' GANTT CHART UPDATE LOG (Day 95 — 2026-04-05) -' Changes: Day 95 cycle-2 refresh. Open PRs: 181→183 (+2). Open bugs: 853→878 (+25 new UAT bugs). -' M3 61% (228/376), M4 57% (104/183), M5 64% (126/196), M6 55% (180/325), -' M7 41% (138/335), M8 41% (359/880), M9 25% (118/465). -' Milestone totals grew significantly: M3 371→376, M4 179→183, M5 191→196, M6 323→325, -' M7 327→335, M8 830→880 (+50 new issues!), M9 464→465. +' Changes: Day 95 cycle-3 refresh. Open PRs: 183→134 (-49 merged!). Open bugs: 878→859 (-19 resolved). +' M3 64% (243/377), M4 58% (107/183), M5 68% (134/198), M6 55% (180/325), +' M7 43% (147/342), M8 44% (394/904), M9 27% (127/467). +' Significant progress: 49 PRs merged, M3/M5/M7/M8/M9 all improved. ' Session 3 active. Session tracker issue: #3377. ' ================================================================ @@ -229,7 +228,7 @@ ganttDiagram { [Decisions + Validations M3 (#357)] as [M3] on {Luis} {Hamza} {Brent} {Jeff} requires 4 days [M3] starts at [M2]'s end -[M3] is 61% completed +[M3] is 64% completed [M3] is colored in LightSkyBlue/SteelBlue ' ── v3.3.0 MILESTONE ───────────────────────────────────────── @@ -250,7 +249,7 @@ ganttDiagram { [Corrections + Checkpoints M4 (#358)] as [M4] on {Luis} {Jeff} {Brent} {Hamza} requires 3 days [M4] starts at [M3]'s end -[M4] is 57% completed +[M4] is 58% completed [M4] is colored in LightSkyBlue/SteelBlue @@ -281,7 +280,7 @@ ganttDiagram { [ACMS v1 + Context Scaling M5 (#359)] as [M5] on {Hamza} {Jeff} {Aditya} {Brent} requires 4 days [M5] starts at [M4]'s end -[M5] is 64% completed +[M5] is 68% completed [M5] is colored in LightSkyBlue/SteelBlue [Autonomy Hardening + Stubs M6 (#360)] as [M6] on {Luis} {Jeff} {Hamza} {Brent} requires 5 days @@ -296,7 +295,7 @@ ganttDiagram { [Large Project Autonomy (#369)] as [LARGE] on {Luis} {Brent} {Jeff} requires 4 days [LARGE] starts 2026-03-17 -[LARGE] is 41% completed +[LARGE] is 43% completed [LARGE] is colored in LightSkyBlue/SteelBlue ' ── v3.5.0 MILESTONE ───────────────────────────────────────── @@ -400,13 +399,13 @@ legend right ---- **Risk Register (Day 95 — 2026-04-05 end-of-day)** |= Epic |= Completion |= Risk |= Blocker | - | M3 (#357) | 61% | **CRITICAL** | 148 open issues in v3.2.0 | - | M4 (#358) | 57% | **CRITICAL** | 79 open issues in v3.3.0 | - | M5 (#359) | 64% | **HIGH** | 70 open issues in v3.4.0 | + | M3 (#357) | 64% | **CRITICAL** | 134 open issues in v3.2.0 | + | M4 (#358) | 58% | **CRITICAL** | 76 open issues in v3.3.0 | + | M5 (#359) | 68% | **HIGH** | 64 open issues in v3.4.0 | | M6 (#360) | 55% | **HIGH** | 145 open issues in v3.5.0 | - | M7 (#361) | 41% | **HIGH** | 197 open issues in v3.6.0 | - | M8 (#362) | 41% | **HIGH** | 521 open issues in v3.7.0 (agent expansion) | - | SEC (#363) | 25% | **HIGH** | 347 open issues in v3.8.0 (agent expansion) | + | M7 (#361) | 43% | **HIGH** | 195 open issues in v3.6.0 | + | M8 (#362) | 44% | **HIGH** | 510 open issues in v3.7.0 (agent expansion) | + | SEC (#363) | 27% | **HIGH** | 340 open issues in v3.8.0 (agent expansion) | ---- **Color Key** |= Color |= Meaning | @@ -418,7 +417,7 @@ legend right ---- 29 Epics | 9 Legendaries | 7 Milestones | 6 Developers ~1649 total story points | ~3300 estimated hours - **878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)** + **859 open bugs — 134 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1951,7 +1950,7 @@ legend right ---- 271 Issues | 29 Epics | 9 Legendaries | 7 Milestones ~1649 total story points | ~3300 estimated hours - **878 open bugs — 183 open PRs — Session 3 active (16 workers, ~71 agents)** + **859 open bugs — 134 open PRs — Session 3 active (16 workers, ~71 agents)** end legend @endgantt @@ -1963,13 +1962,13 @@ This section provides a high-level overview of the CleverAgents implementation r ### Current Status Summary -As of Day 95 (2026-04-05), the project has **183 open PRs** and **~1465 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **878 open bugs** (up from 853 — continued agent-driven UAT bug creation). M8 (v3.7.0) is now **41% complete** (359/880 issues closed — milestone grew dramatically from 830→880, +50 new issues). M9 (v3.8.0) is **25% complete** (118/465 issues closed). M3 (v3.2.0) at **61%** (228/376), M4 (v3.3.0) at **57%** (104/183), M5 (v3.4.0) at **64%** (126/196), M6 (v3.5.0) at **55%** (180/325), M7 (v3.6.0) at **41%** (138/335). +As of Day 95 (2026-04-05), the project has **134 open PRs** and **~1466 open issues** across 9 milestones. **Session 3 is active with full supervisor fleet: 16 parallel workers and ~71 total concurrent agents**. Bug count is **859 open bugs** (down from 878 — 19 resolved). **Significant progress in cycle 3: ~49 PRs merged.** M8 (v3.7.0) is now **44% complete** (394/904 issues closed — improved from 41%). M9 (v3.8.0) is **27% complete** (127/467 issues closed — improved from 25%). M3 (v3.2.0) at **64%** (243/377), M4 (v3.3.0) at **58%** (107/183), M5 (v3.4.0) at **68%** (134/198), M6 (v3.5.0) at **55%** (180/325), M7 (v3.6.0) at **43%** (147/342). -**M1, M2 fully complete. M3 (v3.2.0)**: 61% complete (228/376), 148 open issues. **M4 (v3.3.0)**: 57% complete (104/183), 79 open issues. **M5 (v3.4.0)**: 64% complete (126/196), 70 open issues. **M6 (v3.5.0)**: 55% complete (180/325), 145 open issues. **M7 (v3.6.0)**: 41% complete (138/335), 197 open issues. **M8 (v3.7.0)**: 41% complete (359/880), 521 open issues. **M9 (v3.8.0)**: 25% complete (118/465), 347 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. +**M1, M2 fully complete. M3 (v3.2.0)**: 64% complete (243/377), 134 open issues. **M4 (v3.3.0)**: 58% complete (107/183), 76 open issues. **M5 (v3.4.0)**: 68% complete (134/198), 64 open issues. **M6 (v3.5.0)**: 55% complete (180/325), 145 open issues. **M7 (v3.6.0)**: 43% complete (147/342), 195 open issues. **M8 (v3.7.0)**: 44% complete (394/904), 510 open issues. **M9 (v3.8.0)**: 27% complete (127/467), 340 open issues. All milestones M3-M7 are **overdue**; M8 and M9 are in active v3.7.0/v3.8.0 development. -!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 878 Open Bugs — Session 3 Active (Day 95: Continued Agent Expansion)" +!!! warning "Schedule Risk: All Milestones M3-M7 Overdue — 859 Open Bugs — Session 3 Active (Day 95: Significant PR Merge Wave)" - All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **183** (up from 181). Open bugs at **878** (up from 853 — continued agent-driven UAT bug creation). Session tracker issue: #3377. **Current priorities**: (1) **Triage 878 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 183 open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 41% complete, 521 issues remaining (milestone grew +50 in 30 min). (4) **Clear M3/M4/M5 backlogs** — M3 at 61% (148 open), M4 at 57% (79 open), M5 at 64% (70 open). + All milestones M3 through M7 have passed their target dates. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs at **134** (down from 183 — ~49 PRs merged in cycle 3). Open bugs at **859** (down from 878 — 19 resolved). Session tracker issue: #3377. **Current priorities**: (1) **Triage 859 open bugs** — agent-driven expansion requires systematic review. (2) **Merge 134 remaining open PRs** — TUI features, security fixes, spec compliance. (3) **Continue M8 push** — 44% complete, 510 issues remaining. (4) **Clear M3/M4/M5 backlogs** — M3 at 64% (134 open), M4 at 58% (76 open), M5 at 68% (64 open). ### Parallel Workstreams @@ -2286,18 +2285,18 @@ Items without an assigned milestone represent backlog work to be addressed after ### Schedule Risk Summary -As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **183** (up from 181). Open bugs at **878** (up from 853 — continued agent-driven UAT bug creation). M8 (v3.7.0) at **41% complete** (359/880 closed — milestone grew dramatically from 830→880, +50 new issues in 30 min). M9 (v3.8.0) at **25% complete** (118/465 closed). Session tracker: #3377. Critical path: 183 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 41% with 521 issues remaining; 878 open bugs need TDD counterparts and systematic triage. +As of Day 95 (2026-04-05), all milestones M3 through M7 are **overdue**. The original 7-8 day slippage has grown to **20+ days** for M3-M6. **Session 3 is active with 16 parallel workers (~71 total agents)**. Open PRs now at **134** (down from 183 — ~49 PRs merged in cycle 3). Open bugs at **859** (down from 878 — 19 resolved). M8 (v3.7.0) at **44% complete** (394/904 closed — improved from 41%). M9 (v3.8.0) at **27% complete** (127/467 closed — improved from 25%). Session tracker: #3377. Critical path: 134 open PRs need review and merge; M3/M4/M5/M6/M7 all overdue; M8 at 44% with 510 issues remaining; 859 open bugs need TDD counterparts and systematic triage. **Day 50 planning actions (completed)**: (a) 2 reviewers assigned to all 20 open PRs. (b) Comments posted on #1154 and #1168 recommending closure. (c) Escalation comments on PRs with missing branches. (d) Issue #1206 created for `@tdd_expected_fail` tag cleanup. (e) Timeline updated with Day 50 schedule adherence entry. **Day 53 Session 3 actions**: (a) 16 parallel workers started. (b) 73+ PRs merged including ACMS UKO runtime (#1312), PermissionsScreen TUI (#1307), actor thought blocks (#1298), DatabaseResourceHandler (#1293), ACMS pipeline Phase 2 (#1287), DevcontainerHandler (#1286), async audit (#1279), serve CLI (#1272), LSP hover/definitions (#1240), domain event wiring (#1215), plan prompt command (#1212), M6 E2E tests (#1277), @tdd_expected_fail cleanup (#1229), persona export/import (#1338), first-run experience (#1391), session export/import (#1392). (c) UAT supervisor fleet (cycles 11-131) launched — discovered 100+ spec compliance bugs across CLI rich output, YAML config handling, and actor compiler. (d) Security bug-hunt PRs opened: #1412 (concurrency), #1409 (error handling), #1419 (hardcoded secrets). (e) Late-day: 4 more PRs merged (#1498, #1481, #1479, #1338), 18 new fix PRs opened (#1506-#1517) targeting UAT findings. (f) End-of-day CLI fix wave: 18 more PRs merged (#1574, #1573, #1570, #1569, #1567, #1566, #1565, #1563, #1562, #1558, #1556, #1554 and others) — open bugs reduced from **143 to 6**, open PRs at **74**. **Critical path blockers** (ranked): -1. **183 open PRs need review** — continued agent-driven PR creation. All require review before merge. -2. **878 open bugs need TDD counterparts** — agents created additional bugs throughout Days 54-95. Continued expansion (853→878). -3. **M3-M7 backlog** — 148+79+70+145+197 open issues across M3-M7. All milestones regressed as agents added new issues. -4. **M8 (v3.7.0) at 41%** — 521 issues remaining (milestone grew dramatically from 830→880, +50 in 30 min). Rapid agent-driven expansion. -5. **M9 (v3.8.0) at 25%** — 347 issues remaining (milestone grew from 464→465). Continued expansion. +1. **134 open PRs need review** — down from 183 after ~49 PRs merged in cycle 3. Continued progress needed. +2. **859 open bugs need TDD counterparts** — down from 878 (19 resolved). Continued systematic triage required. +3. **M3-M7 backlog** — 134+76+64+145+195 open issues across M3-M7. M3/M5/M7 improved significantly in cycle 3. +4. **M8 (v3.7.0) at 44%** — 510 issues remaining (improved from 41%/521 — 35 issues closed in cycle 3). +5. **M9 (v3.8.0) at 27%** — 340 issues remaining (improved from 25%/347 — 9 issues closed in cycle 3). **Spec changes impact assessment (Day 31)**: ACP→A2A rename affects 10 source files, 13 classes, 640+ test references across 22 files. Zero A2A code exists — migration not started. All open PRs that touch ACP modules will need additional rebase work after #688/#689 merge. TUI spec adds ~1,500 lines with 18 ASCII mockups defining Textual-based UI — PR #667 was a placeholder that predates this spec. Server architecture adopts JSON-RPC 2.0 standard — PR #676 used custom protocol, now obsolete. @@ -4950,15 +4949,15 @@ Deadline risk: HIGH **Notes** -- Day 95 cycle-2 refresh (2026-04-05). Open PRs: 181→183 (+2 new PRs). Open bugs: 853→878 (+25 new UAT bugs). Total open issues: ~1465. Session tracker issue: #3377. +- Day 95 cycle-3 refresh (2026-04-05). Open PRs: 183→134 (-49 merged!). Open bugs: 878→859 (-19 resolved). Total open issues: ~1466. Session tracker issue: #3377. - Session 3 remains active with 16 parallel workers and ~71 total concurrent agents. UAT pool supervisor, PR reviewer pool, implementation pool, and spec updater agents all running. -- 5 PRs merged earlier today: plan rollback panels (#3279), plan apply panels (#3460), actor remove impact counts (#3463), session field fix (#3461), providers type fix (#3459). Additional PRs opened: 183 total open. -- Milestone totals continued to grow rapidly due to agent-driven issue creation: M3 (371→376), M4 (179→183), M5 (191→196), M6 (323→325), M7 (327→335), M8 (830→880, +50 new issues!), M9 (464→465). -- Milestone completions (Day 95 cycle-2): M3 61% (228/376), M4 57% (104/183), M5 64% (126/196), M6 55% (180/325), M7 41% (138/335), M8 41% (359/880), M9 25% (118/465). -- M8 dropped from 43% to 41% as 50 new issues were added in ~30 minutes — rapid agent-driven expansion. M7 also declined (42%→41%) as 8 new issues were added. +- **Significant PR merge wave in cycle 3**: ~49 PRs merged, bringing open PRs from 183 down to 134. This is the largest single-cycle merge event observed. +- Milestone completions improved significantly (Day 95 cycle-3): M3 64% (243/377), M4 58% (107/183), M5 68% (134/198), M6 55% (180/325), M7 43% (147/342), M8 44% (394/904), M9 27% (127/467). +- M3 improved from 61%→64% (15 issues closed), M5 improved from 64%→68% (8 issues closed), M7 improved from 41%→43% (9 issues closed), M8 improved from 41%→44% (35 issues closed), M9 improved from 25%→27% (9 issues closed). +- Milestone totals continued to grow: M3 (376→377), M7 (335→342), M8 (880→904, +24 new issues), M9 (465→467). - All milestones M3-M7 remain overdue. M8 and M9 have no deadlines and are in active development. -- UAT pool supervisor and spec updater agents are running autonomously, continuing to discover and file spec compliance issues at high velocity. -- New UAT bugs filed include: #3560 (PlanExecutor no subplan spawning), #3561 (SkeletonCompressor not invoked), #3563 (ACMSPipeline single-strategy), #3564 (InvariantReconciliationActor 4-tier vs 3-tier), #3565 (project list format), #3566 (InvariantService DI bypass), #3567 (SubplanService validate_spawn), #3568 (NodeDefinition actor_ref ignored), #3569 (DecisionService dependencies not persisted), #3570 (project show format), #3571 (invariant add scope flag), plus 25+ additional bugs in cycle 2. +- UAT pool supervisor and spec updater agents are running autonomously, continuing to discover and file spec compliance issues. +- New UAT bugs filed include: #3560 (PlanExecutor no subplan spawning), #3561 (SkeletonCompressor not invoked), #3563 (ACMSPipeline single-strategy), #3564 (InvariantReconciliationActor 4-tier vs 3-tier), #3565 (project list format), #3566 (InvariantService DI bypass), #3567 (SubplanService validate_spawn), #3568 (NodeDefinition actor_ref ignored), #3569 (DecisionService dependencies not persisted), #3570 (project show format), #3571 (invariant add scope flag), plus many more across cycles 2-3. #### Milestone forecast @@ -4967,34 +4966,34 @@ Deadline risk: HIGH |-----------|---------------|-------|------| | M1 (v3.0.0) | (2026-02-15) -> COMPLETE | 0d | COMPLETE | | M2 (v3.1.0) | (2026-02-22) -> COMPLETE | 0d | COMPLETE | -| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-12 | +75d | CRITICAL — 148 open issues; agent-driven expansion outpacing closures | -| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-14 | +73d | CRITICAL — 79 open issues; completion at 57% | -| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-14 | +69d | HIGH — 70 open issues; 64% complete | -| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-24 | +75d | HIGH — 145 open issues; 55% complete | -| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-15 | +79d | HIGH — 197 open issues; 41% complete | -| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-15 | N/A | HIGH — 521 open issues; 41% complete (milestone grew +50 in 30 min) | -| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-22 | N/A | MEDIUM — 347 open issues; 25% complete | +| M3 (v3.2.0) | (2026-02-26) -> ETA 2026-05-08 | +71d | CRITICAL — 134 open issues; 64% complete (improved from 61%) | +| M4 (v3.3.0) | (2026-03-02) -> ETA 2026-05-10 | +69d | CRITICAL — 76 open issues; completion at 58% | +| M5 (v3.4.0) | (2026-03-06) -> ETA 2026-05-08 | +63d | HIGH — 64 open issues; 68% complete (improved from 64%) | +| M6 (v3.5.0) | (2026-03-10) -> ETA 2026-05-22 | +73d | HIGH — 145 open issues; 55% complete | +| M7 (v3.6.0) | (2026-03-28) -> ETA 2026-06-08 | +72d | HIGH — 195 open issues; 43% complete (improved from 41%) | +| M8 (v3.7.0) | (no deadline) -> ETA 2026-07-05 | N/A | HIGH — 510 open issues; 44% complete (improved from 41%) | +| M9 (v3.8.0) | (no deadline) -> ETA 2026-07-15 | N/A | MEDIUM — 340 open issues; 27% complete (improved from 25%) | #### Track forecast | Track | Status | ETA | Risk | Blocking | |-------|--------|-----|------|----------| | Track A (Plan lifecycle + persistence) | Complete | Done | LOW | None | -| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-14 | MEDIUM | 70 open issues in v3.4.0; continued agent-driven expansion | -| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-14 | CRITICAL | 79 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion at 57% | -| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-12 | CRITICAL | 148 open issues in v3.2.0; agent-driven expansion outpacing closures | -| Track Q (Quality automation) | Ongoing | N/A | HIGH | 878 open bugs; continued agent-driven bug creation (+25 in 30 min) | -| Track T (Testing) | Active | Ongoing | HIGH | 183 open PRs need review; UAT pool supervisor active (#3377) | +| Track B (Projects/resources + sandbox) | In Progress | ETA 2026-05-08 | MEDIUM | 64 open issues in v3.4.0; 68% complete (improved from 64%) | +| Track C (Actors/tools/skills/validations) | In Progress | ETA 2026-05-10 | CRITICAL | 76 open issues in v3.3.0; UAT spec compliance bugs ongoing; completion at 58% | +| Track D (Change tracking + apply pipeline) | In Progress | ETA 2026-05-08 | CRITICAL | 134 open issues in v3.2.0; 64% complete (improved from 61%) | +| Track Q (Quality automation) | Ongoing | N/A | HIGH | 859 open bugs; down from 878 (19 resolved in cycle 3) | +| Track T (Testing) | Active | Ongoing | HIGH | 134 open PRs need review; ~49 PRs merged in cycle 3; UAT pool supervisor active (#3377) | #### Developer forecast | Name | Days Ahead/Behind | Availability | Risk | Focus | |------|-------------------|--------------|------|-------| -| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 183 open PRs | +| Jeff | -21d behind | active | HIGH | Session 3 supervisor; TUI architecture; M8 push; PostgreSQL backend; A2A compliance; 134 open PRs | | Luis | -21d behind | active | HIGH | M6 (v3.5.0) features; security hardening; audit session; PR review pool | | Hamza | -21d behind | active | HIGH | Resource DAG; v3.6.0 features; AWS CloudResource; PR reviews | | Aditya | -21d behind | active | HIGH | M5 features; TDD counterparts; domain model work; UAT testing | -| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 878 open bugs triage | +| Brent | -21d behind | active | HIGH | Bug fixes; TDD counterparts; quality automation; 859 open bugs triage | | Rui | -21d behind | active | HIGH | TUI features; UAT bug fixes; security bug-hunt; E2E testing | | Mike/Brian | N/A | standby | LOW | N/A | @@ -5006,16 +5005,16 @@ Milestone per developer as of Day 95 end-of-day (2026-04-05). |-----------|------|--------|------|-------|-------|-----|------------|-------| | M1 | 29/29 | 16/16 | N/A | 4/4 | 10/10 | N/A | 35/35 | 96/96 | | M2 | 26/26 | 14/14 | N/A | 1/1 | 5/5 | N/A | 6/6 | 56/56 | -| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 148 open | 228/376 | -| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 79 open | 104/183 | -| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 70 open | 126/196 | +| M3 | N/A | N/A | N/A | N/A | N/A | N/A | 134 open | 243/377 | +| M4 | N/A | N/A | N/A | N/A | N/A | N/A | 76 open | 107/183 | +| M5 | N/A | N/A | N/A | N/A | N/A | N/A | 64 open | 134/198 | | M6 | N/A | N/A | N/A | N/A | N/A | N/A | 145 open | 180/325 | -| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 197 open | 138/335 | -| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 521 open | 359/880 | -| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 347 open | 118/465 | -| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1465 open** | **1249/2814 closed** | +| M7 | N/A | N/A | N/A | N/A | N/A | N/A | 195 open | 147/342 | +| M8 | N/A | N/A | N/A | N/A | N/A | N/A | 510 open | 394/904 | +| M9 | N/A | N/A | N/A | N/A | N/A | N/A | 340 open | 127/467 | +| **Total** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **N/A** | **~1466 open** | **1332/2798 closed** | -Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 cycle-2 refresh (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Agent-driven issue creation continues at high velocity across all milestones. M3 grew from 371→376, M4 grew from 179→183, M5 grew from 191→196, M6 grew from 323→325, M7 grew from 327→335, M8 grew dramatically from 830→880 (+50 new issues in ~30 min), M9 grew from 464→465. Open bugs increased from 853→878 (+25 new UAT bugs). +Note: "done/total" = closed/total for that milestone. Assignee data reflects Forgejo API as of Day 95 cycle-3 refresh (2026-04-05). Most open issues are unassigned or assigned to freemo (Jeff). Significant PR merge wave in cycle 3: ~49 PRs merged, bringing open PRs from 183 to 134. M3 improved from 228→243 closed (15 issues closed), M5 improved from 126→134 closed (8 issues closed), M7 improved from 138→147 closed (9 issues closed), M8 improved from 359→394 closed (35 issues closed), M9 improved from 118→127 closed (9 issues closed). Open bugs decreased from 878→859 (-19 resolved). #### Story point allocation